Area wise Quarters Repair Summary
11.09.2020 to 25.09.2020
Area
Repaired Status of Qtrs of Area
Action for repair of balance quarters
Total No. of quarters (A)
Identified for repairs
(B)
Repairs completed till March 2020
(C)
Repairs done in the fortnight (D)
Total repairs in 2020-21
(E )
Cumulative
repair done till date
(F)= (C )+ (E )
Repair work started (Work order issued) No. of quarters (G)
Repair work yet to start (Work order issued) No. of quarters (H)
Tenders to be finalised for No. of Quarters (I)
Balance to
be repair
Basundhra
468
468
468
---
468
----
----
----
0
Bharatpur
836
836
836
---
836
----
----
----
0
CWS IB
102
101
101
---
101
----
----
----
0
CWS Talcher
294
294
294
---
294
----
----
----
0
Hingula
895
745
745
---
745
----
----
----
0
IB Valley 
1300
1299
1299
---
1299
----
----
----
0
Jagannath 
2140
2035
2035
---
2035
----
----
----
0
Lakhanpur
1865
1765
1765
---
1765
----
----
----
0
Lingraj
899
815
815
---
815
----
----
----
0
NSCH
201
201
201
---
201
----
----
----
0
MCL HQ 
679
613
503
0
27
530
83
0
0
83
Orient 
4122
2286
2237
0
0
2237
49
0
0
49
Talcher
1405
1345
1335
0
10
1345
0
0
0
0
MCL  
15206
12803
12634
0
37
12671
132
0
0
132
Qtr. Repairing Completed(Percentage)
98.97%