Sl. No. |
Name of the Project |
Capacity (Mty) |
EC Letter No. and Date | Half Yearly Compliance Report for Apr'20-Sept'20 |
Capacity (Mty) |
CTE letter No. and Date | Capacity (Mty) |
CTO Letter No. and date |
Valid upto |
HWA letter No. and Date |
Valid upto | Environmental Statements (2019-20) |
---|
1 |
Ananta OCP |
4.00 |
12.00 |
12.00 |
31-03-2018 |
31-03-2019 |
||||||
8.00 |
||||||||||||
12.00 |
||||||||||||
20.00 |
20.00 |
31-03-2024 |
||||||||||
20.00 Amend -ment in EC |
15.00/ 20.00 |
15.00 |
31-03-2019 |
|||||||||
2. |
Jagannath OCP |
6.00 |
6.00 |
6.00 |
31-03-2021 |
31-03-2019 |
||||||
7.50 |
7.50 |
31-03-2020 |
||||||||||
7.50 |
31-03-2021 |
|||||||||||
3. |
Bhubaneswari OCP |
10.00 |
25.00 |
25.00 |
31-03-2021 |
31-03-2019 |
||||||
20.00 |
||||||||||||
25.00 |
||||||||||||
28.00 |
28.00 |
28.00 |
31.03.2021 |
|||||||||
4. |
Balaram OCP (Previously known as Kalinga OCP till 2005-06) |
8.00 |
CTE was not required at that time |
7.74 |
31-03-2020 |
31-03-2020 |
||||||
6.00 |
31-03-2021 |
|||||||||||
5. |
Hingula OCP |
4.00 |
15.00 |
12.00 |
31-03-2019 |
31-03-2020 |
||||||
12.00 |
||||||||||||
15.00 |
10.00 |
31-03-2020 |
||||||||||
31-03-2021 |
||||||||||||
6. |
Lingaraj OCP |
5.00 |
20.00 |
20.00 |
31-03-2020 |
31-03-2021 |
||||||
13.00 |
||||||||||||
20.00 |
13.00 |
31-03-2021 |
||||||||||
7. |
Kaniha OCP |
3.50 |
10.00 |
10.00 |
31-03-2018 |
31-03-2021 |
||||||
10.00 |
||||||||||||
14.00 |
14.00 |
14.00 |
31-03-2020 |
|||||||||
31-03-2021 |
||||||||||||
8. |
Bharatpur OCP |
3.50 |
20.00 |
20.00 |
31-03-2022 |
31-03-2021 |
||||||
15.00 |
||||||||||||
20.00 |
||||||||||||
9. |
Chhendipada OCP |
0.35 |
0.35 |
NIL |
31-03-2020 |
|||||||
10. |
Talcher UG |
0.27 |
CTE was not required when the mine was started |
0.27 |
31-03-2022 |
31-03-2020 |
||||||
11. |
Deulbera UG |
0.20 |
CTE was not required when the mine was started |
Nil |
31-03-2022 |
|||||||
12. |
Nandira UG |
0.33 |
CTE was not required when the mine was started |
0.33 |
31-03-2022 |
31-03-2020 |
||||||
13. |
Natraj UG Project |
0.64 |
0.64 |
0.64 |
31-03-2019 |
|||||||
NIL |
31-03-2022 |
|||||||||||
14. |
Talcher(W) UG |
0.52 |
0.52 |
NIL |
31-03-2017 |
|||||||
15. |
Jagannath UG |
0.67 |
||||||||||
16. |
Samaleswari OCP |
3.00 |
15.00 |
15.00 |
31-03-2020 |
31-03-2021 |
||||||
5.00 |
||||||||||||
11.00 |
||||||||||||
11.00 Area Expansion |
||||||||||||
15.00 |
||||||||||||
15.00 Area Expansion |
31-03-2021 |
|||||||||||
17. |
Lajkura OCP |
1.00 |
4.50 |
4.50 |
31-03-2020 |
31-03-2021 |
||||||
3.00 |
||||||||||||
4.50 |
31-03-2021 |
|||||||||||
18. |
Lakhanpur OCP |
5.00 |
18.75 |
18.75 |
31-03-2018 |
31-03-2021 |
||||||
10.00 |
||||||||||||
15.00 |
||||||||||||
18.75 |
||||||||||||
21.00 (for one year) |
21.00 |
21.00 |
27-02-2020 |
|||||||||
21.00 |
31-03-2021 |
|||||||||||
19. |
Belpahar OCP |
2.00 |
9.00 |
9.00 |
31-03-2020 |
31-03-2023 |
||||||
4.50 |
||||||||||||
6.00 |
||||||||||||
9.00 |
31-03-2021 |
|||||||||||
9.00 (Extn.) |
||||||||||||
20. |
Lilari OCP |
0.80 |
CTE was not required when the mine was started |
0.40 |
31-03-2019 |
31-03-2019 |
||||||
NIL |
31-03-2020 |
|||||||||||
31-03-2021 |
||||||||||||
21. |
Basundhara (E) |
0.60 |
||||||||||
22. |
Basundhara (W) |
2.40 |
7.00 |
7.00 |
31-03-2019 |
|||||||
8.00 |
3.00 |
31-03-2020 |
||||||||||
2.00 |
31-03-2021 |
|||||||||||
23. |
Garjanbahal OCP |
10.00 |
13.00 |
13.00 |
31-03-2021 |
|||||||
13.00 |
||||||||||||
24. |
Kulda OCP |
14.00 |
10.00 |
10.00 |
31-03-2018 |
31-03-2021 |
||||||
14.00 |
14.00 |
31-03-2020 |
||||||||||
31-03-2021 |
||||||||||||
25. |
Orient UG Mine no.1&2 |
0.87 |
CTE was not required when the mine was started |
0.87 |
31-03-2020 |
31-03-2019 |
||||||
31-03-2021 |
||||||||||||
26. |
Orient UG Mine no.3 |
0.69 |
CTE was not required when the mine was started |
0.69 |
31-03-2020 |
|||||||
31-03-2021 |
||||||||||||
27. |
Orient UG Mine no.4 |
0.50 |
CTE was not required when the mine was started |
0.5 |
31-03-2020 |
31-03-2019 |
||||||
0.18 |
31-03-2021 |
|||||||||||
28. |
Hirakhand Bundia Incline |
0.95 |
0.95 |
0.95 |
31-03-2020 |
31-03-2019 |
||||||
31-03-2021 |
||||||||||||
29. |
Hingir Rampur Colliery |
0.398 |
||||||||||
30. |
Kalinga Washery |
8.00 |
||||||||||
31. |
M/s Kanika Railway Siding of Basundhara |
NIL |
NIL |
Letter awaited from project |
60,00,000 (T/Annum) |
31-03-2020 |
||||||
31-03-2021 |
||||||||||||
32. |
Mandapal Sand Mine |
0.25 Million m3/annum |
2,50,000 (Cu.m./ Annum) |
2,50,000 (Cu.m./ Annum) |
31-03-2020 |
|||||||
31-03-2023 | ||||||||||||
33. |
Hingula Washery |
10.00 |
10.00 |
|||||||||
34. |
Jagannath Washery |
10.00 |
10.00 |
|||||||||
10.00 (Amend -ment in EC) |
||||||||||||
10.00 (Amend -ment in EC) |
||||||||||||
35. |
Ib Valley Washery |
10.00 |
10.00 |
|||||||||
10.00 (Amend -ment in EC) |
||||||||||||
36. |
M/s Sardega Railway Siding |
20.00 |
||||||||||
37. |
Basundhara Washery |
10.00 |